the diversion track south of Wallace Street in Toronto near the Davenport Diamond

Next steps for the Davenport Diamond Guideway project

With the temporary diversion track up and running, construction can begin on the elevated guideway.

Sep 8, 2020

As GO trains pass through the section between Bloor Street and Davenport Road, Barrie line customers might not notice they are travelling on track that has been shifted to the side.

Since May 2020, construction on the Davenport Diamond project has been entirely focused on a temporary diversion track.

Looking north from Bloor Street in Toronto, a piece of rail sits on a bed of gravel

Looking north from Bloor Street in Toronto, crews have been working on building the temporary diversion track since May. (Metrolinx photo).

“Getting the diversion track safely up and running was the first major milestone for the Davenport Diamond project. It signals the start of construction on the elevated guideway, making it a significant achievement for all,” said Kent Barber, Metrolinx project lead.

Davenport Diamond Guideway project takes next step in getting customers where they need to go

At Paton Road, a boom truck operator squeezes the rails until they are perfectly spaced apart. (Metrolinx photo).

Most of the diversion track was built in the months leading up to the September long weekend, while trains ran on the main Barrie line. The last few pieces of the puzzle, however, had to be carried out while no trains were in service.

Davenport Diamond Guideway project takes next step in getting customers where they need to go

Left: Original Barrie line track. Right: New temporary diversion track running alongside the original track. (Metrolinx photo).

A major track closure on the Barrie GO line over the September long weekend allowed crews to make the necessary connections between the new diversion track, the existing main line track and the intersecting CP Rail freight tracks.

At the two far ends, crews connected the diversion track to the main line. This is known as a track tie-in, and one connection took place near Bloor Street and the other near Davenport Road.

A closer look at the track components for the temporary diversion track, including the pre-ballas...

A closer look at the track components for the temporary diversion track. (Metrolinx photo).

Crews cut the existing track, pulled it over to line up with the diversion track, and welded the two together. At Bloor, about 80 metres of main line track were pulled over, compared to the 100 metres at Davenport to account for the curve in the track.

North of Dupont Street, where the Barrie GO line meets the CP Rail freight tracks, more connections were made. As the GO track (i.e. the diversion track) now intersects with the CP tracks at a different point, a temporary diamond that aligns with the diversion track was installed at this new intersection. The existing diamond was decommissioned and removed.  

Before the diversion track was built, a couple of major works took place. First was the construction of a shoring wall northeast of the diamond to support the diversion track structure next to an open excavation at the neighbouring development. And second was the relocation of the northeast signal arm at Wallace Avenue to align with the diversion track and maintain safety at this crossing.

Images shows shoring wall construction,

Shoring wall construction just north of the Davenport Diamond. The Davenport Diamond refers to the intersection where the Barrie GO corridor meets the set of CP Rail freight train tracks. (Metrolinx photo.)

the

The shoring wall allows the diversion track to be built next to an open excavated pit. (Metrolinx photo).

The diversion track was built in stages, beginning with clearing and grubbing of vegetation to make room for the new track. Next, grading activities, including laying down sub-ballast, created a strong, even ground. Once a solid foundation was attained, pre-ballast was laid, followed by track and ties, and finished off with ballast.

A graphic showing the different kind of track bed levels, from the ground up the

A closer look at the various track bed levels for the temporary diversion track. (Metrolinx photo).

At 1.7 kilometres long, the diversion track runs from just north of Bloor Street to just north of Davenport Road. 

“The diversion track is the result of a lot of hard work and detailed planning by all parties. Now that it’s successfully in operation, we can shift our focus to the heart of this project, the elevated guideway, and we’re really excited to get started on it,” said Mathew Hanna, Design-Build Director for Graham Commuter Rail Solutions.

With the diversion track up and running, the portion of existing main line no longer in use will be decommissioned and removed to allow construction to begin on the elevated guideway.

the diversion track south of Wallace Street in Toronto near the Davenport Diamond

Photo of the diversion track south of Wallace Street in Toronto near the Davenport Diamond construction (Metrolinx photo).

For more information on the Davenport Diamond Guideway project, click here.

For construction updates and to sign up for the Toronto West e-newsletter, click here.


by Teresa Ko Metrolinx communications senior advisor