A computer rendering showing the elevated section of the Eglinton Crosstown West Extension

Eglinton Crosstown West Extension

Renforth Station

Located at the western end of the route, Renforth Station will serve as a transit hub, connecting to MiWay routes 7, 39, 100, 107 and 109, GO bus routes 19 and 40, and TTC routes 32 and 112.

The future station site is also where Rexy and Renny, the two tunnel boring machines (TBMs) that dug out the western underground segment of the Eglinton Crosstown West Extension, began their journey.

The two TBMs excavated 6.3 kilometres of parallel tunnels before they were disassembled and removed from the extraction shaft just west of Scarlett Road.

Images

A map of the area around Renforth Station showing future Eglinton Crosstown West Extension upgrades
A conceptual rendering of Renforth Station

A conceptual rendering of a new entrance building at Renforth Station.

Drone shot of the tunnel launch site of the Eglinton Crosstown West Extension

A birds-eye view of the tunnel launch site while tunnelling was underway.

Construction timeline

  • Tunnelling started

    April 2022

  • Tunnelling completed

    June 2024

  • SRS development partner named

    August 2025

  • Site cleared

    Current

  • Start of station construction

    Next step

Local construction

Click the icons on the map for the latest notices and other information related to the station.

Get in touch

We're committed to keeping you informed and engaged every step of the way as we build the Eglinton Crosstown West Extension.

Our team is here to answer your questions, address issues, and provide the information you need. Reach out to us any time at EglintonWest@metrolinx.com or via our 24/7 phone line: 416-202-8001.