GO Train on the tracks

Kitchener Line GO Expansion

Bloor Station (TTC Connection)

As part of GO Expansion, Metrolinx is building an accessible underground pedestrian tunnel extension connecting Bloor GO/UP Station to Dundas West TTC Station.

It is estimated that 600 transfers occur between Bloor GO/UP Station and Dundas West TTC Station each day. With the forecasted land development in the area, this number is expected to increase to 1600 by 2041.

When finished, customers will have an accessible and safe pedestrian connection between GO Transit, UP Express and TTC services, to better support customers travelling throughout Toronto.

This project supports the development of a regional rapid transit network that offers seamless connections to more stations and faster trains.

Bloor Station (TTC Connection) project is currently in construction. For more information on project phases, please check out our project lifecycle page.

Project overview

  • Extending the existing south side pedestrian tunnel at Bloor GO/UP Station.
  • A new TTC concourse in the lower level of The Crossways building (within the parking structure) with elevator access to platform level.
  • Two elevators and a stairwell connecting the existing Bloor GO/UP tunnel and the new TTC concourse.
  • A new electrical room with upgraded emergency back-up and life-safety systems.

Photos and renderings

Benefits

  • A much quicker connection between the stations. When the tunnel is complete, the walk will take less than two minutes. Currently, it takes five to eight minutes, depending on traffic, weather, and user mobility.
  • The accessible and barrier-free tunnel, complete with elevators, will help airport passengers with luggage and customers with mobility challenges more easily transfer between GO/UP and TTC.
  • Improved wayfinding will help customers navigate the stations with greater ease.
  • Improved passenger safety:
    • Customers will no longer have to cross mixed traffic (Bloor GO/UP PUDO, Dundas Street West and streetcar tracks)
    • The underground tunnel protects passengers from inclement weather.
    • Extension of the existing closed-circuit television (CCTV), public announcement and overall security systems.

Construction of the connection between the two stations is now underway. To further enhance access to both stations, a new extension of the existing Passenger Pickup and Drop Off (PUDO) and a new dedicated pedestrian pathway about 50 metres closer to Dundas and Bloor intersection will make the access more convenient and safer for customers.

This work is part of a separate contract and funded by Metrolinx.

Project Progress

  • Start of construction

    May 2024

  • Excavation of tunnel complete

    September 2024

  • Construction of pedestrian tunnel wall

    October 2024

  • Construction of underground staircases

    December 2024

  • Jet grouting to strengthen and stabilize soil

    April 2025

  • Underground wall demolition and concrete removal

    December 2025

  • Installation of staircase frame

    January 2026

  • Wall demolition to Dundas West TTC platform

    March 2026

Coming up on site

Continued underground construction - structural reinforcement, waterproofing and staircase forming

Future project milestones

Completion of staircases and elevators to new concourse
Construction of new lower-level concourse
Testing and commissioning
Project completion

Subscribe to e-newsletter

Subscribe for regional updates

Subscribe for the latest news from Metrolinx. You can unsubscribe at any time.