- In late July 2026, Metrolinx contractors will begin site preparation including building a temporary access worksite at Millwood Road and Overlea Boulevard for the construction of guideway foundations and substructure in this area.
- An access gate will be installed along the west side of Millwood Road, north of Overlea Boulevard to manage construction vehicle entry and secure the work site.
- To safely complete this work, there will be a partial southbound bike lane closure on Millwood Road before Overlea Boulevard, with traffic barrels in place to separate the work area from vehicular traffic.
Ontario Line
A new 15.6-km subway line in Toronto that will run from Exhibition Place, through downtown, all the way to Line 5 Eglinton at Don Mills Road.- Projects & Programs
- Ontario Line
- Notices
- Site preparation and access road construction at Millwood and Overlea
Site preparation and access road construction at Millwood and Overlea
Expected Duration
Jul 27, 2026 - Jan 31, 2028
Working Hours
Weekdays from 7 a.m. to 7 p.m.
Date of Notice
Jul 24, 2026
Map for Site preparation and access road construction at Millwood Road and Overlea Boulevard
What is Happening?
What to expect
- Construction of the access worksite is expected to take approximately four weeks and construction activities will occur within the site until late 2028.
- Excavation and grading of the site to provide stable ground for construction equipment.
- Compaction to achieve required surface strength, stability, and erosion control.
- Temporary fencing will be installed along the perimeter of the construction zone.
- Gates will be installed to manage unauthorized vehicles and equipment access to the work site.
- Short-term traffic and cycling interruptions can be expected during trucks and equipment movements into and from the site.
- Construction vehicles and equipment will enter and exit the site from Millwood Road through the new access gates.
- Work may be delayed, rescheduled, or extended due to weather conditions or unforeseen circumstances.
- Access roads will be removed once construction activities are complete, and the area will be restored with topsoil and seed/sod.
- Work may be delayed, rescheduled, or extended due to weather conditions or unforeseen circumstances.
Noise and Vibration
- Residences and businesses in the area may experience noise and vibration caused by construction equipment related to the works. Efforts will be made to minimize noise associated with construction where possible.