Partial Intersection Closure at Signalized Intersection at 7700 Hurontario Street

Expected Duration

Jul 8, 2026 - Aug 13, 2026

Working Hours

Monday to Friday, 7:00 a.m. to 7:00 p.m.

Date of Notice

Jul 9, 2026

Traffic management mapillustratingapartial closureandprohibitedturningmovements at 7700 Hurontario.

What is Happening?

From 8 p.m. on July 8, 2026 to August 13, 2026, crews will be installing guideway and tracks at the signalized intersection at 7700 Hurontario Street. Overnight implementation will happen from July 8, 2026 to July 9, 2026. Left turns will be prohibited while the closure is in place and will be reinstated once work is complete.

What to expect

  • Increased presence of construction vehicles and equipment can be expected in the work area.
  • Work areas will be clearly marked or fenced off to ensure public safety.
  • Please exercise caution around active construction sites.
  • Work may be delayed or rescheduled due to weather or unforeseen circumstances.

Traffic Changes

  • A paid duty officer, flaggers and detour signs will be onsite to direct traffic as needed.
  • All businesses in the area will remain open during the work. Please follow signage for access.

Pedestrian Access

  • Temporary sidewalk closures or pedestrian detours will be in place while the work is underway, with signs in place to direct pedestrians as needed.

Noise and Vibration

  • Residences and businesses in the area may experience noise and vibration caused by construction equipment related to this work.
  • Crews will take measures to minimize disruptions to the surrounding area wherever possible.

Transit Service

  • There is no anticipated impact to transit services.