As part of the improvements being made at King City GO Station, crews working on behalf of Metrolinx are continuing work within the rail corridor in King Township. Activities include grading, followed by the installation of high-security fencing and noise walls to support future service increases on the Barrie Line. Additionally, electrical infrastructure and cable installation work will be conducted to support future electrification of the tracks.
Work has been underway since Fall 2025 and is being completed in phases. Construction activities may occur in different areas of the corridor at different times. Schedules must account for track access requirements, existing utilities that require coordination, and future project phases- including the installation of additional culverts starting Spring 2027.