Lakeshore West Line GO Expansion
- Projects & Programs
- Lakeshore West Line GO Expansion
- Notices
- Road widening works at Burloak Drive
Road widening works at Burloak Drive
Expected Duration
Oct 20, 2026 - Dec 18, 2026
Working Hours
Monday to Friday, 7:00 a.m. to 5:00 p.m.
Date of Notice
Oct 19, 2026
Crews will be working on the curbs, sidewalks, and roads for the future Burloak Drive, Superior Court and Prince William Drive
What is Happening?
Starting October 20, 2026, crews will be working on the curbs, sidewalks, and roads for the future Burloak Drive, Superior Court and Prince William Drive. The Road widening has been broken up into five different stages. Crews are currently working on Stage 1, which is the portion located on the West side of Burloak just north of Prince William Drive. As crews progress through the different stages of the road widening operation, there will be short-term closures to adjacent sidewalks. Detour signage will be posted. There will be reoccurring short-term lane closures along Burloak Drive between the Rebecca/New Street and Harvester/Wyecroft Road intersections for on-going works at the Burloak Grade Separation.
What to expect
- Increased presence of construction vehicles and equipment can be expected in the work area.
- Work areas will be clearly marked or fenced off to ensure public safety.
- Please exercise caution around active construction sites.
Traffic Changes
- Two-way directional traffic will be maintained during the work.
Pedestrian Access
- Pedestrian detours may be required, with signs in place to direct pedestrians as needed.
Noise and Vibration
- Residences and businesses in the area may experience noise and vibration caused by construction equipment related to this work.
Transit Service
- There is no anticipated impact to transit services.