GO train

Lakeshore East Line GO Expansion

Overnight train movements and works on the Lakeshore East rail corridor - September 2026

Expected Duration

Sep 14, 2026 - Oct 5, 2026

Working Hours

Monday to Sunday, 11:00 p.m. to 4:00 a.m.

Date of Notice

Sep 15, 2026

Overnight train movements and works on the Lakeshore East rail corridor - September 2026 - IMG

Map showing the extent of the work area

What is Happening?

We need to position our work trains so they are available for use during the overnight track closures on the Lakeshore East railway corridor. In the run up to these closures, we will be maneuvering our work trains into the sidings in the location shown on the map above, between Greenwood Ave and Woodbine Ave. This will happen overnight when there are no passenger services running on the Lakeshore East corridor. We have shown more time than we expect to use as we cannot forecast exactly when the work trains may be entering or leaving the sidings. These brand-new trains represent a significant improvement on our previous trains and will result in shorter and more efficient overnight work in the coming weeks.

What to expect

  • Increased presence of construction vehicles and equipment can be expected in the work area.

Traffic Changes

  • No disruptions to traffic are anticipated.

Pedestrian Access

  • All pedestrian sidewalks will remain open throughout the work.

Noise and Vibration

  • Residences and businesses in the area may experience noise and vibration caused by construction equipment related to this work.

Transit Service

  • There is no anticipated impact to transit services.