GO Train on the tracks

Kitchener Line GO Expansion

Demolition of 236-254 Old Weston Road Rowhomes

Expected Duration

Nov 9, 2026 - Jan 29, 2027

Working Hours

Monday to Friday, 7:00 a.m. to 5:00 p.m.

Date of Notice

Oct 21, 2026

Demolition of 236-254 Old Weston Road Rowhomes

What is Happening?

As part of preparatory work for the future Stockyards Station, crews will demolish a series of row homes along a stretch of Old Weston Road. This work is a key component in the eventual Westward extension of Davenport Road. All activities will take place behind construction fencing within the limits of private property. Ahead of work activities, the sidewalk along the west side of Old Weston Road will be closed to pedestrian traffic. No closure of Old Weston Road is anticipated. This work is expected to take approximately six weeks to complete, and will occur within the indicated date range. 

What to expect

  • Trucks and construction equipment may generate dust during construction.
  • Crews will take precautions to monitor and reduce dust.
  • Increased presence of construction vehicles and equipment can be expected in the work area.
  • Work areas will be clearly marked or fenced off to ensure public safety.
  • Please exercise caution around active construction sites.
  • Work may be delayed or rescheduled due to weather or unforeseen circumstances.
  • The properties slated for demolition include:

    • 236 Old Weston Road
    • 238 Old Weston Road
    • 240 Old Weston Road
    • 242 Old Weston Road
    • 244 Old Weston Road
    • 246 Old Weston Road
    • 248 Old Weston Road
    • 250 Old Weston Road
    • 252 Old Weston Road
    • 254 Old Weston Road

Traffic Changes

  • No disruptions to traffic are anticipated.

Pedestrian Access

  • Temporary sidewalk closures or pedestrian detours will be in place while the work is underway, with signs in place to direct pedestrians as needed.

Noise and Vibration

  • Residences and businesses in the area may experience noise and vibration caused by construction equipment related to this work.
  • Crews will take measures to minimize disruptions to the surrounding area wherever possible.
  • To minimize noise impacts on the community, noise monitoring equipment will be installed prior to construction. These devices will help to detect exceedances early to proactively conduct corrective actions as needed while crews work.
  • Trucks accessing the site will be equipped with broadband backup alarms, which emit a less disruptive sound compared to traditional beeping backup alarms.

Transit Service

  • There is no anticipated impact to transit services.